Project Morpheus successfully conducts free flight 7

by Chris Bergin

Project Morpheus – an experimental lander project – has enjoyed a successful free flight at its test range at the end of the Shuttle Landing Facility (SLF) on Monday. Previously delayed by poor weather at the Kennedy Space Center (KSC) – along with technical issues – Monday’s free flight achieved another milestone for the technology demostrator that may be adopted by future commercial lunar landers.

Morpheus Rises:

Manufactured and assembled at JSC and Armadillo Aerospace, the Morpheus system is large enough to carry 1,100 pounds of cargo to the moon.

This cargo capability includes the ability to transport a humanoid robot, a small rover, or even a small laboratory to convert moon dust into oxygen.

Morpheus is designed as a full spacecraft system, with all the associated subsystems: avionics; software; guidance, navigation and control; power; power distribution; structures; propulsion; and instrumentation.

By NASA standards, the project is run via minimal funding, with a small team of around 30 people.

It was heavily associated with a project to send a version of the Robonaut – like the one currently on the International Space Station (ISS) –  to the Moon. This was known as Project M (documentation available in L2).

This notional mission would see the robot and lander launched from KSC on a commercial expendable launch vehicle and inserted into a trans-lunar trajectory.

Once at the moon, the spacecraft would be inserted into a low lunar orbit where it would orbit until ready to perform the entry, descent, and landing (EDL).

The focus of the project is now aimed more at Morpheus being a vertical test bed demonstrating green propellant propulsion systems and autonomous landing and hazard detection technology.

The system is a prototype lander engineers can use to integrate technologies for future spacecraft that could land on a variety of destinations in our solar system.

Working on the fine-tuning of the vehicle’s control and stability, 19 tethered tests were conducted on Morpheus through to 2012 at JSC.

Morpheus then made its way to the Shuttle Landing Facility (SLF) at KSC, ahead of attempting its first free flight over a specially constructed hazard field of craters and rocks at the end of the runway.

Z3However, the test – conducted in August of last year – did not go to plan, as the vehicle’s Thrust Vector Control (TVC) system suffer a major malfunction, sending it into a roll, prior to crashing into the ground.

Although SLF fire crews were on hand, the pressurized system could not be approached as it laid crippled on the site.

Eventually, the fire breached the pressurized fuel tanks, resulting in it exploding.

The Morpheus team, now combined with the Autonomous Landing Hazard Avoidance Technology (ALHAT) team members, were then directed to build the Morpheus 1.5B and 1.5C vehicles, ahead of a return to static hot fire and dynamic tethered flight tests at JSC in early 2013.

Z4At the end of October, the lander’s engine was successfully ignited six times in a row, with each burn lasted 600 milliseconds.

This period of testing was challenging, resulting in the test schedule at KSC to be delayed several times.

In November, the vehicle was transported to the T-Shelter at the Kennedy Space Center, in preparation for a series of free flight tests.

All KSC testing has been conducted without incident during its second visit to Florida.

Z3Monday’s test was known as Free Flight 7, successfully increasing the distance the vehicle rose to, with 465 feet the altitude for this latest test, with a translation across the ground of 630 or so feet.

In preparation for the test – and the associated risks – KSC staff were told surrounding areas will be restricted.

“Due to the untethered test flight of the Morpheus vehicle on 10 Feb, temporary road closures of up to 30 minutes should be expected at the following locations from 1200-1630 hours,” noted the release.

“State Road 402 (Beach Road) & Kennedy Parkway (Wilson’s Corner):  No southbound or westbound traffic will be allowed. State Road 402 (Beach Road), east of Oak Hammock:  No eastbound traffic will be allowed. Kennedy Parkway, just north of the C-Band RADAR site (Bldg. J6-407):  No northbound traffic will be allowed.”

Morpheus has mutliple safety controls including onboard soft abort systems and a wireless Flight Termination System.

In the end, the test, which began just after 18:00 UTC, was a success, with only a small fire caused on the field, which was no threat to the vehicle.

Z6Should the remainder of free flights work as planned, the next stage will be to install a sensor package designed to detect and avoid hazards on the ground.

The hazard area had already been constructed at the end of the SLF, resembling a mini lunar surface area. These tests area currently expected to take place in March and April of this year.

Providing the test series is a success, Morpheus could then directly contribute to numerous technology goals.

The project has been openly promoted to commercial companies interested in future lunar landings, such as Golden Spike.

(Images: Via L2 content. Other images via NASA)

(L2 is – as it has been for the past several years – providing full exclusive SLS and Exploration Planning coverage.  To join L2, click here: http://www.nasaspaceflight.com/l2/)

Related Articles