NASA teams take SLS through fueling test to inform launch date

by Chris Gebhardt

As part of continued troubleshooting and seal replacement validation efforts, teams at the Kennedy Space Center in Florida took the SLS rocket through a Core Stage and Interim Cryogenic Propulsion System (ICPS) fueling test on Wednesday, Sept. 21. NASA officials hoped the test would reveal no leaks of the liquid hydrogen (LH2) system, which has so far plagued the agency in all fueling operations where the commodity was loaded onto SLS at the pad.

That did not pan out, but the test was completed successfully.

With the fueling test complete, should the Eastern Range subsequently approve a waiver for the rocket’s Flight Termination System batteries, NASA might be able to attempt a launch of SLS on the Artemis I mission as soon as Sept. 27.

UPDATE

While the initial “kinder, gentler” fueling process seemed to work during LH2 chilldown and slow fill operations, a leak in the same spot at the same time with the same leak rate indication was observed in the eight-inch quick disconnect seal that malfunctioned on the Sept. 3 launch attempt.

Teams stopped that leak, with concentrations dropping to 0.5% ambient concentration and peaking back to only 3.4% during engine bleed kick start instead of seven percent as originally observed earlier.

From there, fueling operations continued, and teams took SLS through a final pre-pressurization test of the Core Stage LH2 tank. This was completed; however, the four-inch quick disconnect seal for LH2 leaked at five percent maximum concentration.

The test was not a firm confirmation that work to stop the LH2 leaks is complete, but might give enough confidence to proceed toward Sept. 27.

Focus on the seals”

NASA was quick to stress on Sept. 19, before count operations for the fueling test began, that this was only a fueling test that was going to “focus on the seals,” said Tom Whitmeyer, Deputy Associate Administrator for Common Exploration Systems Development.

According to NASA, the fueling test for the Core Stage and ICPS will see teams initiate engine bleed and thermal conditioning on the RS-25 engines, pre-pressurization demonstration, and monitoring of the Core Stage LH2 tank “for a period of time,” noted Whitmeyer.

Numerous agency officials stressed that the count would not reach the T-10 minute and holding mark and that teams will not enter the terminal count.

Furthermore, the Orion spacecraft and the twin Solid Rocket Boosters flanking the Core Stage will not be powered on for the fueling test. NASA officials also noted that no range assets or input will be required for the Sept. 21 test.

A particular point of the test is taking the entire system through a “kinder, gentler loading operation.”

Whereas liquid oxygen has a density similar to water and requires pumps to move the commodity from its storage facility in the northwest section of Pad 39B to the rocket and up into the tanks, liquid hydrogen is different. Being less dense, pumps are not required, and pressure is used instead to move LH2 from its commodity sphere on the northeast side of the pad to the Mobile Launcher and up into the vehicle.

This use of pressure, as well as the sequencing of when chilldown operations to thermally condition the LH2 systems for fueling operations begin, is part of a multi-branch fault tree analysis NASA is using to mitigate any potential issues with the system.

The LH2 flare stack is visible during the second Artemis I launch attempt on Sept. 3. (Credit: Jack Beyer for NSF)

Parts of the new procedures involve using a lower LH2 pressure at the beginning of chilldown operations. The new, lower-pressure environment will be used up until fast-fill operations for the Core Stage begin.

Test teams arrived on console in the Launch Control Center, a moment called “Call to Stations,” at 3 PM EDT (19:00 UTC) on Monday, Sept. 19.

Tuesday saw teams perform final walk-downs of the vehicle, mobile launch tower, and launchpad itself before ensuring that all gaseous nitrogen (GN2) systems were properly configured.

The blast danger area was then cleared of all nonessential personnel at T-9 hours, or 3:40 AM EDT (07:40 UTC) Wednesday morning.

Air-to-GN2 handover then took place at the T-7-hour 15-minute mark, after which point a 2.5-hour built-in hold began. During this hold, test teams are expected to give a go for loading operations.

Under a nominal timeline, the pre-pressurization test will come around 1 PM EDT (17:00 UTC) at the T-2-hour 18-minute mark in the countdown. This will be followed by a wrap of all critical operations by 3 PM EDT (19:00 UTC).

Need for the test

The need for the Sept. 21 tanking test stems from a major leak of LH2 at the 20-cm (eight-inch) quick disconnect seal on the Tail Service Mast Umbilical (TSMU) during the Sept. 3 launch attempt.

During that attempt, the amount of hydrogen in the ambient air of the enclosed umbilical breached NASA’s four percent conservative safety limit. Hazardous gas detectors registered an eight percent concentration that was repeated during the multiple attempts to fix the seal issue.

In the ambient air, hydrogen begins to cause a flammability concern at four percent concentration. NASA inserts the cavities inside TSMU with helium, thus removing the oxidizer to prevent the ignition of hydrogen even if its concentration breaches the ambient flammability concern limit.

Following a forward path to remove and replace the suspect seal, as well as other seals and soft goods on the TSMU at the pad ahead of a fueling test, engineers and technicians identified a 0.02-cm (0.01-inch) witness mark or defect/indentation in the seal.

This witness mark would normally be indicative of Foreign Object Debris (FOD); however, numerous closeout photographs of the system show no FOD present in the area.

NASA officials pointed out that FOD was only one potential cause of the defect on the seal and that the over-pressurization event and thermal issues seen during the Sept. 3 attempt could also be contributing factors given that the seal performed perfectly during the Aug. 29 launch attempt.

Forward path to launch

Pending the outcome of the fueling test on Sept. 21, NASA’s options for launch remain somewhat nebulous in terms of when SLS might lift off on its first launch. Complicating matters is the need to properly review all data from the fueling test before committing to a launch. And that assumes the fueling test reveals no further leaks or issues.

Artemis I at LC-39B. (Credit: Julia Bergeron for NSF)

Further complicating the situation are the Flight Termination System (FTS) batteries onboard SLS, which have breached their certification limit of 25 days. That previous certification ended on Sept. 6, and the Eastern Range is responsible for utilizing the FTS should the rocket deviate from course and the need to protect air, land, and sea assets arises.

NASA has submitted paperwork and documentation to Eastern Range officials showing that they believe the FTS batteries are still within certification parameters. If this is held true, a waiver can be issued by the Range to permit the Sept. 27 and Oct. 2 launch attempts without the need to roll SLS back to the Vehicle Assembly Building to retest the FTS batteries.

However, the Range is not expected to issue a decision until after that fueling test is complete, and it is possible that yet more data will be needed from NASA for a decision to be reached.

“We need to see where those discussions take us,” noted Whitmeyer. “We’re being respectful of their process.”

From NASA’s perspective, the next major formal decision point following the Sept. 21 test will come on Sunday, Sept. 25 during the L-2 day Mission Management Team meeting.

Artemis I at LC-39B. (Credit: Stephen Marr for NSF)

It is at this meeting that all formal waivers will be formally discussed and accepted (usually) and at which the final decision from the agency as to whether or not to proceed to a launch attempt on Sept. 27 will be reached.

However, NASA officials noted that a decision could come earlier than Sunday should the fueling test go well and the Eastern Range provide their answer.

The 70-minute launch window on Sept. 27 opens at 11:37 AM EDT (15:37 UTC) and would result in a 39-day, long-class mission of Orion into its Near Rectilinear Halo Orbit of the Moon.

If for whatever reason SLS is not able to lift off on Sept. 27, a backup opportunity is available on Oct. 2 during a 109-minute long launch window that opens at 2:52 PM EDT (18:52 UTC).

The Oct. 2 launch would also result in a long-class mission with a landing in the first half of November.

(Lead photo: SLS at LC-39B at the conclusion of Wednesday’s fueling test. Credit: Stephen Marr for NSF)